9 Essential Steps to Master Earned Value Analysis for Project Managers
By Alvin Villanueva, PMP; Editor: Geram Lompon; Reviewed by: Grace Payumo, PMP
Many project managers struggle with tracking progress, predicting outcomes, and staying within budget, leading to surprises that derail their goals. You don’t have to be one of them.
Imagine having the power to foresee your project’s success before it’s too late to make a difference.
Earned Value Analysis (EVA) is the ultimate solution for controlling projects and will serve as your early warning system. It helps you measure cost and schedule performance, forecast results, and make confident decisions based on complex data. Whether you manage a small team or oversee a complex initiative, EVA equips you with the clarity and precision to lead confidently.
Ready to eliminate the guesswork in
Let’s explore further!
Earned Value Analysis Explained: What It Is and Why It Matters
Earned Value Analysis (EVA) is your go-to strategy for effective project control (Terrell & Richards, 2018).
Think of it as a crystal ball for your project—showing you exactly where things stand and where they’re headed. By comparing the work you’ve completed so far to your planned, budgeted cost and schedule, EVA lets you spot risks, forecast outcomes, and make smarter decisions before minor issues snowball into big problems.
It’s not just about tracking—it’s about staying ahead and keeping your project on the path to success. EVA allows you to make decisions based on real-time data, empowering you to assess project performance, forecast potential roadblocks, and take proactive action.
Top Reasons to Learn Earned Value Analysis and Improve Your Projects
Knowing your project’s status isn’t just helpful; it’s essential. Without a clear understanding of where you stand, it’s easy to overspend, miss deadlines, or lose sight of your goals.
Here are the top reasons Earned Value Analysis helps with your projects:
- EVA gives the project team and you the power to stay in control, turning uncertainty into confidence and chaos into clarity.
- It keeps you proactive, not reactive. By identifying potential issues early, you can make adjustments before they escalate. EVA allows you to access timely and accurate data and to make informed decisions based on data, not just gut feeling.
- It aligns the project’s progress with goals. EVA ensures the work being done matches the project’s original plan, so there are no surprises.
- It helps you justify decisions. Complex data from EVA supports your calls on budgets, complex projects, timelines, and resource allocation.
- It’s a universal metric. Whether reporting to your team, clients, or stakeholders, EVA offers objective performance metrics in a common language everyone can understand.
- It predicts the future. With EVA, you can confidently forecast outcomes, setting yourself up for success.
The strength of Earned Value Analysis is its adaptability. It works for projects of any size and complexity. By learning this method, you equip yourself with a reliable management system to track, measure, and optimize your project’s performance at every step.
Let’s dive into how you can use EVA to transform how you manage projects..
Methods of Earned Value Analysis
Understanding the methods of Earned Value Analysis (EVA) is essential for keeping your project’s completion and your projects on track. These methods allow you to measure progress, predict outcomes, and make informed decisions before minor issues become major problems.
You can effectively control your budget and schedule with the right approach to value management while delivering consistent results.
1. Variance Analysis
Variance Analysis evaluates whether your project is ahead, behind, over budget, or under budget. It focuses on two key metrics: Schedule Variance (SV) and Cost Variance (CV).
- Schedule Variance (SV): Indicates whether a project is ahead of or behind schedule.
- Formula: SV = EV – PV
- Metrics:
- SV > 0: Ahead of schedule.
- SV = 0: On schedule.
- SV < 0: Behind schedule.
- Example: If Earned Value (EV) is $8,000 and Planned Value (PV) is $10,000, then:
SV = $8,000 – $10,000 = -$2,000 (The project is $2,000 behind schedule.)
- Cost Variance (CV): Shows whether the project is over or under budget.
- Formula: CV = EV – AC
- Metrics:
- CV > 0: Under budget.
- CV = 0: On budget.
- CV < 0: Over budget.
- Example: If EV is $8,000 and Actual Cost (AC) is $7,500, then:
CV = $8,000 – $7,500 = $500 (The project is $500 under budget.)
2. Performance Indices
Performance indices provide efficiency ratios to evaluate actual performance, time utilization and other direct costs and resources.
- Schedule Performance Index (SPI): Measures schedule efficiency.
- Formula: SPI = EV / PV
- Metrics:
- SPI > 1: Ahead of schedule.
- SPI = 1: On schedule.
- SPI < 1: Behind schedule.
- Example: If EV is $8,000 and PV is $10,000, then:
SPI = $8,000 / $10,000 = 0.8 (The project is progressing at 80% of the planned schedule vs performance measurement baseline and is behind schedule.)
- Cost Performance Index (CPI): Assesses cost efficiency.
- Formula: CPI = EV / AC
- Metrics:
- CPI > 1: Under budget.
- CPI = 1: On budget.
- CPI < 1: Over budget.
- Example: If EV is $8,000 and AC is $7,500, then:
CPI = $8,000 / $7,500 = 1.07 (The project generates $1.07 in value for every dollar spent and is underspending.)
How to Perform Earned Value Analysis: Step-by-Step Guide
Gaining proficiency in Earned Value Analysis (EVA) is like learning a secret formula for successful
This step-by-step guide will walk you through the process, breaking it down into manageable and engaging steps.
Step 1: Determine Percent Complete
How to Execute This Step:
- Break tasks into manageable components if necessary, ensuring you can evaluate progress accurately.
- For smaller tasks (those requiring less than 80 hours), use the 0%, 50%, or 100% rule:
- 0%: Not started.
- 50%: In progress.
- 100%: Complete.
- Count measurable units completed for repetitive tasks (e.g., number of items installed or code modules written).
Step 2: Calculate Planned Value (PV)
How to Execute This Step:
- Reference the project schedule to determine how much work should have been completed.
- Multiply the task budget by this percentage to calculate its PV.
- Example: If a task has a budget of $5,000 and is scheduled to be 60% complete, then:
- PV = $5,000 x 60% = $3,000
Step 3: Determine Earned Value (EV)
How to Execute This Step:
- Use the percent complete for each task to calculate its EV.
- Multiply the task budget by the percent complete.
- Example: If a task has a budget of $5,000 and is 40% complete, then EV = $5,000 x 40% = $2,000
Step 4: Obtain Actual Cost (AC)
How to Execute This Step:
- Gather cost data for each completed task from your
project management or accounting systems. - Include all relevant expenses (labor, materials, etc.)
- Example: If labor costs are $800, materials cost $500, and equipment rentals cost $200 for a task, then AC = $1,500
Step 5: Calculate Variances (SV and CV)
How to Execute This Step:
- Calculate Schedule Variance (SV):
- SV = EV – PV.
Example: If EV = $8,000 and PV = $10,000, SV = -$2,000 (behind schedule). - Calculate Cost Variance (CV):
CV = EV – AC.
Example: If EV = $8,000 and AC = $7,500, then CV = $500 (under budget).
Step 6: Measure Efficiency (SPI and CPI)
How to Execute This Step:
- Schedule Performance Index (SPI): SPI = EV / PV. If EV is $8,000 and PV is $10,000, SPI = 0.8 (behind schedule).
- Cost Performance Index (CPI): CPI = EV / AC. If EV is $8,000 and AC is $7,500, CPI = 1.07 (underspending).
Step 7: Forecast the Future (EAC, ETC)
How to Execute This Step:
- Estimate at Completion (EAC):
- EAC = AC + (BAC – EV).
Example: If AC = $7,500, BAC = $20,000, EV = $8,000, EAC = $19,500 (project coming in under budget). - Estimate to Complete (ETC):
ETC = EAC – AC.
Example: If EAC = $19,500 and AC = $7,500, then ETC = $12,000.
Key Considerations for Successfully Performing Earned Value Analysis
- Accurate Baseline Data: Ensure the baseline (budget and schedule) is precise for effective tracking.
- Consistent Tracking: Regular updates are essential for real-time project monitoring.
- Effective Communication: Share your findings with stakeholders in an actionable way using visuals like S-curves or burn-up charts (Garling, 2021).
Taking It to the Next Level
To elevate your EVA process, consider incorporating advanced
Earned Value Analysis vs. Alternatives
While EVA is robust, other methods may work better and suit specific projects:
- Agile Methods: Works well for iterative projects with visual metrics like burn-down charts.
- Critical Path Method (CPM): Focuses on managing the task sequence for time-sensitive projects.
- Rolling Wave Planning : Ideal for projects with high uncertainty and evolving requirements.
By developing proficiency in Earned Value Analysis and leveraging these advanced methods, you’ll be equipped to lead your future projects confidently and clearly.
References
A practical guide to earned value
Chitas, N. (2014). How can Earned Value Management and Lean improve a
Earned Value Management in easy steps. (n.d.). Google Books. https://books.google.com.ph/books?hl=en&lr=&id=g244DwAAQBAJ&oi=fnd&pg=PT6&dq=Earned+Value+Analysis+instructions,+template,+with+examples&ots=1rsoZec-37&sig=A4C0ufAatTCYnpsgF_gZWjYLgn4&redir_esc=y#v=onepage&q&f=false
Earned Value management using Microsoft® Office Project. (n.d.). Google Books. https://books.google.com.ph/books?hl=en&lr=&id=brrdqpTsdOoC&oi=fnd&pg=PR5&dq=Earned+Value+Analysis+instructions,+template,+with+examples&ots=e8EZC9OOi8&sig=jcvtszCURQO6DWEIMucXc3UMP8E&redir_esc=y#v=onepage&q=Earned%20Value%20Analysis%20instructions%2C%20template%2C%20with%20examples&f=false
Garling, V. a. P. B. R. (2021, February 15). Artificial intelligence and earned value in
Greenburg, D., Michalaka, D., & Shick, M. (2022). An integrated exercise to teach earned value management. In American Society for Engineering Education & The Citadel, School of Engineering, 2022 ASEE Southeastern Section Conference. https://sites.asee.org/se/wp-content/uploads/sites/56/2022/03/2022ASEESE18.pdf
Häkkinen, M. (2015). The Earned Value in
Maggert, A. S. (2009). Earned Value management as a means to mitigate DOD contract fraud (By University of Wisconsin-Platteville & Graduate Facility). https://minds.wisconsin.edu/bitstream/handle/1793/34273/MaggertAnthonyS.pdf?sequence=4
Managing projects as investments . (n.d.). Google Books. https://books.google.com.ph/books?hl=en&lr=&id=5q34EAAAQBAJ&oi=fnd&pg=PP1&dq=Earned+Value+Analysis+instructions,+template,+with+examples&ots=3D1qAO1iZr&sig=R8aNgjjqPbaWI0Q_N_k49jY0q6g&redir_esc=y#v=onepage&q&f=false
Salmi, A. (2018, September 24). Applying earned value management in construction project . https://aaltodoc.aalto.fi/items/6e362bb2-9491-4b09-8688-5341639ce149
Terrell, S. M., & Richards, B. W. (2018, January 1). Earned Value Management (EVM) Implementation Handbook. NASA Technical Reports Server (NTRS).https://ntrs.nasa.gov/citations/20180001499
Keywords: to complete performance index